5.11. Time-Phased Rough Cut Capacity Plan by Work Center

To view a rough cut capacity plan by work center showing detail over calendar periods you define, go to Schedule > Reports > Time-Phased Rough Cut Capacity Plan. The following screen will appear:

Time-Phased Rough Cut Capacity Plan

When displaying a time-phased rough cut capacity plan by work center, you are presented with the following options:

All Work Centers

Select to display time-phased rough cut capacity plan by work center for all work centers.

Selected

Specify work center whose time-phased rough cut capacity plan you want to display.

All Sites

Select to display time-phased rough cut capacity plan by work center for all sites.

Selected

Specify site whose time-phased rough cut capacity plan by work center you want to display.

Calendar

Select the calendar you want to use for the report. Associated calendar periods will be displayed.

Name/Selected Periods

Select as many periods as you want to display. Selected periods correspond to calendar specified in the Calendar field. Select individual periods or groups of periods together. To select an individual period, highlight the period using your mouse button. The period is now selected. To select a sequence of periods, highlight the first in the sequence using your mouse button. Then, holding down the SHIFT key on your keyboard, highlight the last period in the sequence. The entire sequence is now selected. To select periods that are out of sequence (e.g., January, April, July, October), highlight the first period in the group. Then, holding down the CTRL key on your keyboard, highlight the next period you want to select. Continue highlighting periods with the CTRL key depressed until all desired periods are selected. The entire group is now selected.

Rough Cut

Display lists time-phased rough cut capacity plan by work center, using the specified parameters.