1. Overview

Purchasing and material requirements planning (MRP) can be used not only for reorder levels but also to capture demand that comes from open sales orders. Stock material can have reorder levels updated in a few different ways:

Item Site record

Go to Inventory > Item Site > List. Open an item site record and the reorder levels can be found under the Planning tab.

Reorder Utility

Go to Inventory > Utilities > Update Item Controls > Reorder Levels. Here you will find three options: per item, per planner code, and per class code. See the following for more information on running the utility: http://www.xtuple.org/sites/default/files/refguide/current/ch02s11s03s04.html